Project Description
- Construction of Mezzanine / Office Fit out, 400m2 within existing warehouse unit
- Steel framed mezzanine with steel staircase, and plasterboard & glass exterior walls
- Complete office fit out including office, meeting room, kitchen, amenities
- Bright colours compliment timber finishes with a smart and modern architectural design
- Addition of skylights creating a bright office connected to the outside world
- This project required a WHS Management Plan which was maintained throughout the project
- Key aspects of safety included strict controls in external carpark area / traffic control, heavy lifting equipment for steel structure and, working at heights.
- Regular site safety checks were performed along with staff inductions and regular tool box talks
- Waste materials were recycled where possible or disposed of accordingly at recognised waste control facilities